Palm Beach County Agricultural Area
Site Assessment/Limited Scope Remedial Action
Prior to purchase of a farm equipment maintenance facility, a due diligence investigation was performed to identify potential environmental liability associated with the property. During the investigation widespread petroleum, arsenic and to a lesser extent pesticide compounds were discovered in the soil and/or groundwater. Therefore an Interim Source Removal Work Plan was submitted to the Florida Department of Environmental Protection (FDEP) for approval. At this juncture AM Environmental was retained to conduct Source Removal and preparation of a Site Assessment Report.
AM performed an extensive Source Removal encompassing removal of an estimated 2600 cubic yards of petroleum impacted soil. Soils were loaded into dump trucks and transported one mile away to be remediated by land farming on an asphalt paved roadway. Land farming of soils resulted in significant savings for the client by alleviating disposal and transportation fees. The excavated area measuring 250 feet by 80 feet, was removed to one foot below the water table and left open to remediate groundwater by natural processes, through aeration and volatilization. In addition, side walls of the excavation were pressure washed on a periodic basis to leach out contaminates binding to exposed layers of muck.
Subsequent to backfilling with clean fill, results from monitoring wells installed around the perimeter of the excavation currently comply with State of Florida Groundwater Cleanup Target Levels. Consequently, the Site Assessment Report was approved by the FDEP with recommendations to develop a limited scope remedial action plan (LSRAP) to reduce the benzene concentration of an isolated plume where buried debris was excavated at another location of the property.
The LSRAP was accomplished by excavating a remedial trench beneath a covered area of the maintenance building. Petroleum contaminated soil and buried debris including; oil containers, tractor parts and treated wood were removed from the trench. Remediation of groundwater in the vicinity of the trench was conducted with open pit air-sparging and simultaneous treatment of exposed water with a bioaugmentation microbial product. The Post Active Remediation Monitoring phase has been completed and the Department of Environmental Protection has approved a Provisional No Further Action proposal for conditional closure of the site.
In summary, by employing alternative methods such as; letting groundwater naturally attenuate, pressure washing side walls of excavation, land farming petroleum contaminated soil in lieu of disposal/tramsportation and performing open pit air-sparging with microbial treatment verses traditonal insitu methods, AM easily saved the client tens of thousands of dollars while still effectively remediating the site.
“AM Environmental has consulted for US Sugar Corporation for the past 10 years. We have been extremely pleased with the quality, efficiency and practicality of their work. AM Environmental's thorough knowledge of Florida DEP regulations and procedures has assured us both excellent results and speedy dispositions. AM Environmental is the first one I call whenever I have a remediation, or due diligence issue.”
-Andy Esposito, Safety & Environmental Manager, US Sugar employee since 1992
Site Assessment for Golf Course Maintenance Area
AM was contacted by a client requesting assistance with a letter from the FDEP requesting additional assessment for historical pesticide contamination at a golf course maintenance shed. Subsequent to reviewing previous site investigations, AM developed a Scope of Work to address remnant concentrations of pesticide compounds, kepone and dieldrin, detected in the soil. The FDEP approved the proposed Scope of Work which called for analytical testing by the synthetic precipitation leaching procedure (SPLP), specifically for the two compounds. Analytical results from the prescribed testing verified that soil and groundwater quality complied with applicable State standards. Ultimately a Site Rehabilitation Completion Order (SRCO) was issued by the State and the case was closed without requiring soil excavation or groundwater remediation.
“When the DEP called and stated that there was chemical contaminates located on the property from years before and would not issue us a new operator’s license until it was resolved; I did not know where to turn. I started calling around and found AM Environmental. AM Environmental responded quickly, was straight forward, efficient and very detailed about the work that needed to be done to correct the situation. Our questions were answered in a timely manner with answers that a layperson, like me, could understand. All of the reports to the DEP were very thorough. We will most definitely contact AM Environmental in the future if needed to handle ALL our environmental questions, remediation or any other environmental concern. Thank you again!”
-Christy-
Potable Water Testing for Motor Yachts
To comply with the Maritime Labour Convention (2006), motor yachts should develop a Fresh Water Safety Plan. A fundamental part of the Plan includes testing drinking water systems on a regular basis for the safety of passengers and crew. AM Environmental provides analysis from NELAC accredited laboratories that are also ELITE certified by the Centers for Disease Control. Fresh water samples are collected from vessels and analyzed for a select suite of inorganics, metals, Legionella and other microbiological parameters included within the Primary/Secondary Drinking Water Standards of Florida and EPA Drinking Water Regulations. A report explaining the laboratory results is included as part of our service as well as recommendations, if warranted.
Beach Renourishment Project
A Baseline (Pre) and Post Project Limited Soil/Groundwater Assessment Report was prepared by AM Environmental for a contractor using private property as an equipment staging area for a truck-in beach renourishment project at a municipality in South Florida. Soil samples were obtained from high traffic areas and groundwater samples were collected from monitoring wells in the vicinity of on-site fueling operations. Laboratory analysis was performed on an extensive list of parameters to verify that environmental conditions of the property had not been compromised.
Karnak Corporation Port Everglades, Fl
Regulatory Investigation for Air Permit & Amend Storage Tank Registration
AM Environmental was authorized to perform regulatory investigation for an industrial facility that manufactures various roof coating and sealing products by mixing asphalt, fibers, gel structure and limestone. The purpose of the investigation was two-fold, firstly to determine if an air permit is required by the Florida Department of Environmental Protection (DEP) and Broward County and secondly if an amendment to the DEP and Broward County storage tank license is warranted for changing the contents of one of the registered aboveground storage tanks (ASTs).
During the site inspection the Plant Manager indicated that three mixing tanks and a hopper previously used for dispensing asbestos were no longer in use. The Broward County Air Section was notified that asbestos containing materials were no longer used in the manufacture process. As such, a modification was requested to change the status of their permit from Title V to a General Air Permit. However, by eliminating asbestos from the manufacture process and ceasing the source of a pollutant-emitting activity, criteria was met for a Generic Facility Exemption in accordance with Air General Permits, Rule 62-210.310 F.A.C.
As a result of the regulatory investigation it was determined that an air permit was no longer required for the facility. In addition to the air permit our regulatory investigation disclosed exemptions that ultimately saved our client from amending the Storage Tank license and paying applicable registration fees.
“The Karnak Corporation retained the services of AM Environmental to perform a Regulatory Investigation for Air Permitting in our Manufacturing Facility located in Ft. Lauderdale Florida. In addition, we needed to amend our Florida DEP Storage Tank Registration for a new raw material. Am Environmental responded in a timely, professional manner to inspect our facility for compliance. After a thorough investigation was completed, the report submitted back to Karnak was straight forward and detailed. Karnak Corporation will continue to use AM Environmental for all of our Environmental Compliance questions, needs, or reporting.”
-Sincerely, Sean G. Smith (Karnak Director of Manfacturing)
Ware's Creek
Dredging /Soil Sampling Plan & Disposal Analysis
AM Environmental, LLC (AM) was retained. to develop and implement a Soil Sampling Plan for modifying the DEP permit portion of the U.S. Army Corps of Engineers Environmental Resource Permit. The purpose of the modification was to verify soil quality of proposed upland excavation from widening Ware's Creek in Bradenton, Florida. Analytical results from additional soil sampling was utilized to better characterize the volume of soil requiring disposal and which landfill would be suitable to accept excavated soil and sediments.
Lease property in West Palm Beach
Limited Phase II Environmental Site Assessment
After review of my client's Lease Agreement/Hazardous Waste Indemnity, AM recommended that a limited due diligence inspection and soil testing be performed to document if the warehouse property was impacted by hazardous materials prior to occupancy. Interviews with my client (the prospective tenant) and photographs confirmed that a drum believed to contain waste solvent was stored on the property. The drum apparently spilled onto the soil and ran into a nearby storm drain. During the due diligence inspection AM personnel observed soil staining, distressed vegetation and stained pavement leading to the drain. In addition several oil stains compromised the integrity of the asphalt pavement and likely penetrated the underlying soil.
Consequently, a soil sample collected adjacent to the drum staging area was analyzed at a NELAC accredited laboratory for solvent compounds. The analytical results for the soil sample identified concentrations of nine regulated compounds that exceeded applicable soil cleanup target levels pursuant to Chapter 62-777 of the Florida Administrative Code (FAC). The compounds detected were consistent with constituents found in solvents and verified pre-existing contamination which was instrumental in relieving my client from liability for the cleanup.
“When we first leased our shop in an industrial neighborhood we suspected there may have been toxic dumping. AM Environmental took the time to consult with us and recommend the test that needed to be done. As suspected there were contaminates. Thanks to their thorough report our landlord is now responsible for the clean-up.”